Impact of Political Factors on Construction Contract Termination: Empirical Evidence From Ghana
DOI:
https://doi.org/10.26437/ajar.v11i3.1161Keywords:
Contract. construction. political factors. project deliverables. terminationAbstract
Purpose: This study aims to identify the political factors that lead to the termination of construction contracts in Ghana.
Design/Methodology/Approach: A quantitative research design was employed, utilising purposive and random sampling techniques to collect data from 315 respondents, comprising project managers, procurement officers, contract managers, architects, engineers, quantity surveyors, and lecturers from Technical Universities in Ghana. Data were analysed using factor analysis, structural equation modelling (SEM), and confirmatory factor analysis (CFA) to explore the effects of political factors on contract termination.
Findings: The results indicate that political factors, including corruption, government violations of clauses, executive leadership changes, poor governance, and a lack of political will, significantly contribute to construction contract terminations. These factors lead to project delays, disputes, and ultimately terminations, highlighting the need for improved governance and risk mitigation strategies in the construction industry.
Research Limitation: The study is limited to the construction industry in Ghana and may not account for industry-specific dynamics in other countries.
Practical Implication: Suggested measures addressing political instability, improving governance, and minimising political interference could significantly reduce contract terminations in Ghana’s construction sector.
Social Implication: There is a need for policy reforms and governance improvements in Ghana’s construction sector. By addressing political instability and promoting transparency, contract terminations could be minimised, leading to better infrastructure development.
Originality/Value: This study introduces empirically validated political variables, such as executive leadership change, government clause violations, and a lack of political will and continuity, that expand existing knowledge on construction contract termination.
References
Abdel-Galil, E., Ibrahim, A. H., & Alborkan, A. (2022). Assessment of transaction costs for
Construction projects. International Journal of Construction Management, 22(9),
pp.1618-1631.
Abd-El-Fattah, S. M. (2010). Structural equation modeling with AMOS: basic concepts, applications and programming. Journal of applied quantitative methods, 5(2), 365–368.
Abdul-Malak, M. A. U., Demachkieh, F. S., & Dhaini, K. Y. (2023). Revoking the Exercised
Termination of the Construction Contract: Implications and Lessons Learned. Journal of
Legal Affairs and Dispute Resolution in Engineering and Construction, 15(3), p.05023001.
Ade-Ojo, O. C., Akinola, J. A., Arijeloye, B. T., & Gabriel, O. S. (2017). Implication of construction contract termination for infrastructural development in Ekiti State local government areas, Nigeria. FUTY Journal of the Environment, 11(1), 32–40.
Adil, A., & Kamal, A. (2019). Authentic leadership and psychological capital in job demands-resources model among Pakistani university teachers. International Journal of Leadership
Adjei, K. O. (2020). A model for predicting cost control practice in the Ghanaian construction industry. PhD Thesis, University of Johannesburg (South Africa).
Akwei, C., Damoah, I. S., & Amankwah‐Amoah, J. (2020). The effects of politics on the implementation of government programs/projects: insights from a developing economy. Politics & Policy, 48(6), 1161–1201.
Alshihri, S., Al-Gahtani, K., & Almohsen, A. (2022). Risk factors that lead to time and cost
overruns of building projects in Saudi Arabia. Buildings, 12(7), p.902.
Ameyaw, E. E., Pärn, E., Chan, A. P., Owusu-Manu, D. G., Edwards, D. J., & Darko, A. (2017).
Corrupt Practices in the Construction Industry: A Survey of Ghanaian Experience. Journal of
Management in Engineering, 33(6), 05017006.
Amoatey, C. T., Ameyaw, Y. A., Adaku, E., & Famiyeh, S. (2015). Analysing delay causes and
effects in Ghanaian state housing construction projects. International Journal of Managing
Projects in Business, 8(1), 198-214.
Appiah, M., Onifade, S. T., & Gyamfi, B. A. (2022). Building critical infrastructures: Evaluating
the roles of governance and institutions in infrastructural developments in Sub-Saharan
African countries. Evaluation Review, 46(4), 391-415.
Awortwi, N. (2012). Contracting out local government services to private agents: An analysis of
contract design and service delivery performance in Ghana. International Journal of Public
Administration, 35(13), 886-900.
Baijal, S. (2024). India Infrastructure Reviving Private Investments
Https://content.knightfrank.com/research/2945/documents/en/india-india-infrastructure- reviving-private-investiments [Accessed:23/04/25]
Bean, G. J. &Bowen, N. K., (2021). Item response theory and confirmatory factor analysis:
Complementary approaches for scale development. Journal of Evidence-Based Social
Work, 18(6), 597-618.
Brown, T. A. (2015). Confirmatory Factor Analysis for Applied Research (2nd ed.). New York: The Guilford Press.
Bryman, A. (2011). Research methods in the study of leadership. The SAGE Handbook of
leadership, 15-28.
Byrne, B. M. (2013). Structural equation modeling with Mplus: Basic concepts, applications, and programming. Routledge.
Chang, T., Deng, X., Hwang, B. G. & Zhao, X. (2018). Political risk paths in international construction projects: Case study from Chinese construction enterprises. Advances in Civil Engineering, 2018(1), p.6939828.
Coffie, G. H., Abeka, H. K., Adzivor, E. K., & Afetorgbor, E. K. (2025). Investigating The Drivers of Cost and Schedule Performance in Ghana's Road Construction. African Journal of Applied Research, 11(3), 21-46.
Coleman, C. E., Mwanaumo, E. M., & Rahman, R. A. (2023). May. Indicators of failing projects: The case of public construction. In AIP Conference Proceedings (Vol. 2688, No. 1). AIP Publishing.
Coleman, C. E., Mwanaumo, E. M., Muya, M. & Rahman, R. A. (2025). Financial challenges leading to premature contract termination in Ghanaian construction industry: Causes and mitigation strategies. Journal of Construction Business and Management, 7(2), 45-66.
Coleman, C. E., Mwanaumo, E. M., Muya, M. & Rahman, R.A. (2025). Influence of technical
challenges on construction project contracting. International Journal of Industrial
Management, 19(2), pp.92-103.
Damoah, I. S., & Kumi, D. K. (2018). Causes of government construction projects' failure in an
emerging economy: Evidence from Ghana. International Journal of Managing Projects in
Business, 11(3), 558-582.
Damoah, I. S., Mouzughi, Y., & Kumi, D. K. (2020). The effects of government construction projects abandonment: stakeholders’ perspective. International Journal of Construction Management, 20(5), 462–479.
Eja, K. M. & Ramegowda, M. (2020). Government project failure in developing countries: A review with particular reference to Nigeria. Journal de la Recherche Scientifique de l’Université de Lomé, 21(4-1), pp.56-64.
Ebekozien, A. (2020). Corrupt acts in the Nigerian construction industry: is the ruling party fighting corruption. Journal of Contemporary African Studies, 38(3), 348-365.
Field, A. P., & Gillett, R. (2010). How to do a meta‐analysis. British Journal of Mathematical and Statistical Psychology, 63(3), 665-694.
Fugar, F. D., & Agyakwah-Baah, A. B. (2010). Delays in Building Construction Projects in Ghana. Construction Economics and Building, 10(1-2), 103-116.
Goldberger, J. (2023). Termination of a construction contract. Commercial Law Quarterly: The Journal of the Commercial Law Association of Australia, 37(4), 17-28.
Hair, J. F., Ringle, C. M., & Sarstedt, M. (2011). PLS-SEM: Indeed, a silver bullet. Journal of Marketing theory and Practice, 19(2), 139-152.
Hu, L. T., & Bentler, P. M. (1999). Cut-off criteria for fit indexes in covariance structure analysis: Conventional criteria versus new alternatives. Structural equation modeling: a multidisciplinary journal, 6(1), 1-55.
Jensen, M. C., & Meckling, W. H. (1976). Theory of the firm: Managerial behavior, agency costs and ownership structure. In Corporate governance (pp. 77-132). Gower.
Jiya, V. H., Ogunleye, E., Onuzulike, C., Akande, E. O., & Tiza, M. T. (2023). Value Management in the Nigerian Construction Industry: Challenges and Prospects. Journal of Management Studies and Development, 2(02), 88-116.
Kissi, E., Asare, O. A., Agyekum, K., Agyemang, D. Y., & Labaran, M. (2019). Ascertaining the
interaction effects among organisational citizenship behaviour, work overload and
employees’ performance in the Ghanaian construction industry. International Journal of
Productivity and Performance Management, 68(7), 1235-1249.
Kley, H. M, Nani, G., & Baiden, B. K. (2019). Studying the use of Termination as a project cost control technique in the construction industry, KNUST. (MSc. Thesis).
Kostritsky, J. P. (2018). A Bargaining Dynamic Transaction Cost Approach to Understanding
Framework Contracts. Am. UL Rev., 68, p.1621.
Laxsana, S., Abiramy, S. & Fayasa, A. F., (2023), July. Measures to mitigate termination of construction contracts in Sri Lanka. In Proceedings of the 11th World Construction Symposium, Sri Lanka (pp. 21-22).
Li, H., Arditi, D. & Wang, Z. (2015). Determinants of transaction costs in construction
projects. Journal of Civil Engineering and Management, 21(5), pp.548-558.
Lühmann, T., Hänseler, P., Grant, B., & Hall, H. (2009). The induction of cell alignment by
covalently immobilized gradients of the 6th Ig-like domain of cell adhesion molecule L1 in
D-fibrin matrices. Biomaterials, 30(27), 4503-4512.
Njuguna, G. N. (2018). Determinants for adoption of quality management system in project
implementation: a case of Nyandarua County Government Construction Projects,
Kenya (Doctoral dissertation, University of Nairobi).
Nor, N. M., & Misnan, M. S. (2024). Issues in Termination of Construction Contract: Based on Law Cases. International Journal of Research and Innovation in Social Science, 8(1), 671-683.
Ofori, G. (2012). New perspectives on construction in developing countries. Routledge.
Owusu-Manu, D. G., Ghansah, F. A., Ayarkwa, J., Edwards, D. J., & Hosseini, R. (2022). Factors influencing the decision to adopt Smart Building Technology (SBT) in developing countries. African Journal of Science, Technology, Innovation and Development, 14(3), 790-800.
Owusu, E. K., Chan, A.P., & Shan, M. (2019). Causal factors of corruption in construction project management: An overview. Science and engineering ethics, 25, pp.1-31.
Osei-Kyei, R., & Chan, A. P. (2017). Empirical comparison of critical success factors for public-private partnerships in developing and developed countries: a case of Ghana and Hong Kong. Engineering, Construction and Architectural Management, 24(6),
Panda, B. & Leepsa, N. M. (2017). Agency theory: Review of theory and evidence on
problems and perspectives. Indian journal of corporate governance, 10(1), pp.74-95.
Pradhananga, P., Elzomor, M., & Santi Kasabdji, G. (2021). Barriers and drivers to the adoption of sustainable construction practices in developing countries: a case study of Venezuela. Journal of Architectural Engineering, 27(3), 05021005.
Radhakrishna, R. B. (2007). Tips for Developing and Testing Questionnaires/Instruments. Journal of Extension, 45(1); 1- 4.
Rose-Ackerman, S., & Palifka, B. J. (2016). Corruption and government: Causes, consequences, and reform. Cambridge University Press.
Smith, L. F. P. (2001). Development of a multidimensional labour satisfaction questionnaire: dimensions, validity, and internal reliability. BMJ Quality & Safety, 10(1), 17-22.
Sanda, Y. N., Anigbogu, N. A., Izam, Y. D., & Datukun, H. L. (2021). Developing questionnaire for post graduate studies in construction management. Journal of Surveying, Construction and Property, 12(1), 17-26.
Siddiqui, Z. N., 2017. Understanding the Linkage among Public Procurement (PP), Corruption,
and Tax Morale (TM) Through Agency Theory (AT): A Review. Business & Economic
Review, 9(3), pp.258-288.
Stumpfegger, E. (2017). Trustworthiness of Research. University of Applied Sciences. Munich
Business School.
https://www.munich-business- school.de/insights/en/2017/trustworthiness-of- research
[Accessed: 17/06/2025]
Seale, C. (1999). Quality in Qualitative Research, Qualitative Inquiry, 5(4), 465–478.
Tang, M., Wang, Y., & Yang, Y. (2023). Political influences of stakeholders on early termination of Public-Private Partnerships: A study on China’s toll road projects. Public Performance & Management Review, 46(6), 1354-1381.
Williams, M. (2016). The Political Economy of Unfinished Development Projects: Corruption, Clientelism, or Collective Choice? This draft: Work in progress.
Williamson, O. E. (1985). Assessing the contract. The Journal of Law, Economics, and Organisation, 1(1), 177–208.
World Bank. (2020). Global economic prospects. World Bank.
Xiong, Z., Xia, H., Ni, J. & Hu, H. (2025). Basic Assumptions, Core Connotations, and Path
Methods of Model Modification -Using Confirmatory Factor Analysis as an example.
In Frontiers in Education (Vol. 10, p. 1506415).
Zhou, X., (2023). Principal-Agent Relationship and Agency Problem. Advances in Economics,
Management and Political Sciences, 34, 74-82.
Downloads
Published
Issue
Section
Categories
License
Copyright (c) 2025 AFRICAN JOURNAL OF APPLIED RESEARCH

This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.
By submitting and publishing your articles in the African Journal of Applied Research, you agree to transfer the copyright of the Article from the authors to the Journal ( African Journal of Applied Research).