Enhancing Productivity in Construction Trades in Labour-Intensive Construction Projects
DOI:
https://doi.org/10.26437/ajar.v11i2.1041Keywords:
Construction. labour-intesive. management. productivity. workerAbstract
Purpose: The study sought to investigate the factors impacting productivity in labour-intensive construction projects, focusing on bricklaying and concreting in Zambia.
Design/Methodology/Approach: This study adopted structured interviews and a questionnaire to collect data for the dependent and independent variables. The independent variables were project-related, management-related, labour-related and industry-related factors, while labour productivity was the dependent variable. 150 sets of questionnaire were administered to stakeholders in the construction industry, and a response rate of 81% was obtained. The primary data was evaluated for validity and reliability and analysed using Statistical Package for Social Sciences software. The analysis revealed a positive and significant relationship between the factors of the independent variables and the dependent variable.
Findings: The data analysis revealed a positive and significant relationship between factors of the independent variables and the dependent variable. Among the research findings were the 36 key factors affecting productivity identified from the literature review and grouped as project-related, management-related, labour-related and industry-related. The extent of the impact of each factor on construction labour productivity was also established using descriptive statistics. The management and project-related factors were found to have the highest impact on workers’ productivity.
Research Limitation: The study was limited to bricklaying and concreting trades. Other trades must be examined to check if the results are similar.
Practical Implication: Manpower planning and human resource management help improve the workforce's efficiency, thereby substantially increasing the number of youth and adults with relevant technical and vocational skills.
Social Implication: Labour productivity helps create meaningful employment, decent jobs, and entrepreneurship opportunities.
Originality/Value: The study sought to identify the factors impacting productivity in labour-intensive construction projects, explore the most critical variables and develop a model to improve construction output and build capacity.
References
Abdelaal, M., Emam, H. & Farrell, P., (2015). Improving workflow in construction projects in
GCC. The 2nd International Conference on Buildings, Construction and Environmental Engineering (BCEE2), Lebanon.
Abdel-Hamid, M. & Mohamed Abdelhaleem, H., (2022). Impact of poor labor productivity on
Construction project cost. International Journal of Construction Management, 22(12), 2356-2363.
Ahmed, S.M., Azhar, S., Castillo, M. & Kappagantula, P., (2002). Construction delays in
Florida: An empirical study. Final report. Department of Community Affairs, Florida, US.
Alaloul, W. S., Musarat, M. A., Rabbani, M. B. A., Iqbal, Q., Maqsoom, A. & Farooq, W.,
(2021). Construction Sector Contribution to Economic Stability: Malaysian GDP Distribution. Sustainability, 13(9), p.5012.
Alinaitwe, H. M., Mwakali, J. A. & Hansson, B., (2007). Factors affecting the productivity of
Building craftsmen‐studies of Uganda. Journal of Civil Engineering and Management, 13(3), pp.169-176.
Allmon, E., Haas, C. T., Borcherding, J. D. & Goodrum, P.M., (2000). US Construction Labor
Productivity Trends, 1970–1998. Journal of construction engineering and management, 126(2), 97-104.
Almamlook, R., Bzizi, M., Al-Kbisbeh, M., Ali, T., & Almajiri, E., (2020). Factors affecting
labour productivity in the construction industry. American Journal of Environmental Science and Engineering, 4(2), 24-30.
Alyew, A., Bassa, M., Reta, A. & Tora, M., (2020). A Study on Factors Affecting Labour
Productivity on Construction Projects in Wolaita Zone, Ethiopia. Int. J. Eng. Res, 8(12), pp.817-822.
Assaad, R.H., El-Adaway, I.H., Hastak, M. & LaScola Needy, K., (2023). Key factors affecting
labor productivity in offsite construction projects. Journal of Construction Engineering and Management, 149(1), p.04022158.
Attar, A.A., Gupta, A.K. & Desai, D.B., (2012). A study of various factors affecting labour
productivity and methods to improve it. IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE), 1(3), pp.11–14.
Austin, P. C., & Steyerberg, E. W., (2015). The number of subjects per variable required in
linear regression analyses. Journal of Clinical Epidemiology, 68(6), 627-636.
Baldwin, L.M., Klabunde, C.N., Green, P., Barlow, W. & Wright, G., (2006). In search of the
perfect comorbidity measure for use with administrative claims data: does it exist? Medical care, 44(8), 745–753.
Bamfo-Agyei, E., Aigbavboa, C., & Thwala, W. D. (2022). Measuring productivity of labour-
intensive work practices in road construction in Africa. Routledge.
Bamfo-Agyei, E., Aigbavboa, C., & Thwala, W. D. (2019). Measuring labour productivity in
labour-intensive works on road construction in Ghana. In Advances in Human Factors, Sustainable Urban Planning and Infrastructure: Proceedings of the AHFE 2018 International Conference on Human Factors, Sustainable Urban Planning and Infrastructure, July 21-25, 2018, Loews Sapphire Falls Resort at Universal Studios, Orlando, Florida, USA 9 (pp. 515-523). Springer International Publishing.
Bamfo-Agyei, E., Thwala, D. W., & Aigbavboa, C. (2023). Optimisation of labourintensive
productivity for construction projects in Ghana. Acta Structilia, 30(1), 122-154.
Bamfo-Agyei, E., Thwala, D. W., & Aigbavboa, C. O. (2020). Influence of workforce on
productivity of labour-intensive works on feeder road construction in Ghana. African Journal of Applied Research, 6(1), 91-104.
Becker, G. S. (1964). Human Capital New York. Columbia University for the National Bureau
of Economic Research.
Bodapati, S.N., (2003). Perspective on construction in the USA. Construction Information
Quarterly, Volume 5 Number 4, pp 3-7, The Chartered Institute of Building.
Borg, L., & Högberg, L., (2014). Organization of laundry facility types and energy use in
owner-occupied multi-family buildings in Sweden. Sustainability, 6(6), 3843-3860.
Cheelo C. & Liebenthal R., (2020). The Construction Sector in Zambia In Mining for Change:
Natural Resources and Industry in Africa. J. Page and F. Tarp (Ed), Oxford University Press.
Chen J.J., (1998). The Characteristics and current status of China’s construction industry,
Construction Management and Economics, 16, pp 711-719
Cheung, S. O., Wong, P. S. P., Fung, A. S. and Coffey, W. V., (2006). Predicting project
performance through neural networks. International Journal of Project Management, 24(3), pp.207-215.
Chi, P., (2019). Working environment and labor efficiency of state owned enterprises and
foreign corporations in Vietnam. Retrived on, 1, p.2022.
Chia, R., (2002). The Production of Management Knowledge: Strategies for Reducing Cost
and Improving Service, Pitman Publishing, London.
Chia, W. K., Teo, M., Wang, W. W., Lee, B., Ang, S.F., Tai, W. M., Chee, C. L., Ng, J., Kan,
R., Lim, W. T. & Tan, S. H., (2014). Adoptive T-cell transfer and chemotherapy in the first-line treatment of metastatic and/or locally recurrent nasopharyngeal carcinoma. Molecular Therapy, 22(1), pp.132-139.
Chinyio, E. A., Olomolaiye, P. O., Kometa, S. T. & Harris, F. C., (1998). A needs-based
methodology for classifying construction clients and selecting contractors. Construction Management & Economics, 16(1), 91–98.
Choi, K., Choe, C., & Lee, D., (2021). The effect of employing temporary workers on
efficiency: Evidence from a meta-frontier analysis. SAGE Open, 11(4), 21582440211058199.
Choi, K., Lee, H.W., Bae, J. & Bilbo, D., (2016). Time-cost performance effect of change
orders from accelerated contract provisions. Journal of Construction Engineering and Management, 142(3), p.04015085.
Chukwudi, K. C., Osibanjo, A. O., Bolodeoku, P. B., Ogunyemi, I. O., Ipelke, J. F., &
Okpalaoka, C., 2022. The impact of monitoring and evaluation of learning and development outcomes on employee productivity. Academy of Strategic Management Journal, 21, 1-15.
Dainty A. R. J, Ison S. G. & Root D. S., (2004). Bridging the skills gap: a regionally driven
strategy for resolving the construction labour market crisis, Engineering, Construction and Architectural Management, Volume 11, (4), 275–283.
Dai, J., Goodrum, P.M. and Maloney, W.F., (2009). Construction craft workers’ perceptions
of the factors affecting their productivity. Journal of Construction Engineering and Management, 135(3), 217–226.
Dilawer, S.A., 2014. Control the loss of labor productivity. Int. J. Civ. Struct. Eng. Res., 2(1),
pp.104-110.
Enshassi, A., Mohamed, S., Mustafa, Z. A., & Mayer, P. E., (2007). Factors affecting labour
productivity in building projects in the Gaza Strip. Journal of civil engineering and management, 13(4), 245–254.
Gal, P.N., (2013). Measuring total factor productivity at the firm level using OECD-ORBIS.
George D, & Mallery, P., (2003). SPSS for Windows step by step: A simple guide and
reference. 11.0 update 4th edition Boston: Allyn & Bacon.
Gopal, T.S.R. & Murali, K., (2015). A critical review of factors influencing labour productivity
in construction. IOSR Journal of Mechanical and Civil Engineering, 12(5), 47-51.
Hai, D. T., & Van Tam, N., 2019. Application of the regression model for evaluating factors
affecting construction workers’ labour productivity in Vietnam. The Open Construction & Building Technology Journal, 13(1).
Halwatura, R. U., (2015). Critical factors which govern labour productivity in the building
construction industry in Sri Lanka. PM World Journal, 4(4), pp.1-13.
Herbsman, Z. & Ellis, R., (1990). Research of factors influencing construction
productivity. Construction Management and Economics, 8(1), pp.49-61.
Hernesniemi H., M. Lammi, and P. Ylä-Anttila; P. Rouvinen (ed.), (1996). ‘Advantage
Finland: The Future of Finnish Industries’. Research Institute of the Finnish Economy (ETLA) and Finnish National Fund for Research and Development (SITRA). Helsinki: Taloustieto Oy.
Heshmati, A. and Rashidghalam, M., (2018). Labour productivity in Kenyan manufacturing
and service industries (pp. 259–286). Springer International Publishing.
Hickson, B. G., & Ellis, L. A., (2014). Factors affecting construction labour productivity in
Trinidad and Tobago. The Journal of the Association of Professional Engineers of Trinidad and Tobago, 42(1), 4–11.
Hiyassat, M. A., Hiyari, M. A., & Sweis, G. J., (2016). Factors affecting construction labour
productivity: a case study of Jordan. International Journal of Construction Management, 16(2), 138-149.
Horman, M. J. & Kenley, R., (2005). Quantifying levels of wasted time in construction with
meta-analysis. Journal of construction engineering and management, 131(1), 52-61.
Horner, R. M. W., Talhouni, B. T. & Thomas H. R., (1989). Preliminary Results of Major
Labour Productivity Monitoring Program. Proceedings of the 3rd Yugoslavian Symposium on Construction Management, Cavtat, 18-28.
Hu, X., & Liu, C., (2017). Total factor productivity measurement with carbon
reduction. Engineering, construction and architectural management, 24(4), 575-592.
Jarkas, A.M. & Bitar, C.G., (2012). Factors affecting construction labor productivity in
Kuwait. Journal of Construction Engineering and Management, 138(7), pp.811-820.
Jarkas, A. M., & Haupt, T. C., (2015). Major construction risk factors considered by general
contractors in Qatar. Journal of Engineering, Design and Technology, 13(1), 165-194.
Irfan, M., Zahoor, H., Abbas, M. & Ali, Y. (2020). Determinants of labor productivity for
building projects in Pakistan. Journal of Construction Engineering, Management & Innovation, 3(2), 85–100.
İşgören, N.Ç., Çınar, A., Tektaş, N., Oral, B., Büyükpehlivan, G., Ulusman, L., Öznaz, D.,
Polat, Z. & Uzmanoğlu, S., (2009). The importance of cooperation between vocational schools and industry. Procedia-Social and Behavioral Sciences, 1(1), pp.1313-1317.
Kaoma, C. & Muya, M., (2016). Artisan Gaps in the Construction Industry in
Zambia. American Scientific Research Journal for Engineering, Technology, and Sciences (ASRJETS), 18(1), 235-251.
Kirchberger, M., (2020). The Construction Sector in Developing Countries: Some Key
Issues. Mining for Change, pp.51-73.
Kyei, P., & Bamfo-Agyei, E. (2021). Determining Labour Productivity for Masonry Works on
Construction Sites. African Journal of Applied Research, 7(1), 17-26.
Lewis, T.M., 2009. Quantifying the GDP Construction Relationship Economics for Modern
Built Environmental. London: Taylor and Francis, pp.34-59
Lim, V.K., (1996). Job insecurity and its outcomes: Moderating effects of work-based and
nonwork-based social support. Human relations, 49(2), pp.171–194.
Liu, Z., Liu, J., Hu, R., Yang, B., Huang, X. &Yang, L., (2023). Calendar events' influence on
the relationship between metro ridership and the built environment: A heterogeneous effect analysis in Shenzhen, China. Tunnelling and Underground Space Technology, 141, p.105388.
Mahamid, I., (2020). Study of relationship between rework and labor productivity in Building
Construction Projects. Revista de la construcción, 19(1), 30-40.
Makulsawatudom, A., Emsley, M. and Sinthawanarong, K., 2004. Critical factors influencing
construction productivity in Thailand. The journal of KMITNB, 14 (3), pp.1-6.
Makulsawatudom, A. & Emsley, M., (2003), March. Factors affecting the productivity of the
construction industry in Thailand: The foremen's perception. In Construction Research Congress: Wind of Change: Integration and Innovation (pp. 1-10).
Mattoussi, W., & M. Ayadi., (2017). ‘The Dynamics of Exporting and Innovation’. Journal of
African Economies, 26(1): 52–66.
Ministry of Works and Supply, (2006). Government of Republic of Zambia, Draft Policy for
Public-Private Partnerships, Lusaka.
Mirahadi, F. & Zayed, T., (2016). Simulation-based construction productivity forecast using
neural-network-driven fuzzy reasoning. Automation in Construction, 65, pp.102-115.
Moselhi, O. & Khan, Z., (2012). Significance ranking of parameters impacting construction
labour productivity. Construction Innovation, 12(3), pp.272-296.
Muhammad, N. Z., Sani, A., Muhammad, A., Balubaid, S., Ituma, E. E., & Suleiman, J. H.,
(2015). Evaluation of factors affecting labour productivity in construction industry: a case study. Jurnal Teknologi, 77(12), 87-91.
Muhwezi, L., Acai, J. & Otim, G., (2014). An assessment of the factors causing delays on
building construction projects in Uganda. International Journal of Construction Engineering and Management, 3(1), 13-23.
Murari, S. S., & Joshi, A. M., (2019). Factors affecting labour productivity in precast
construction industry. In Proceedings of the fourth national conference on road and infrastructure.
Muya, M., Price, A.D.F. and Edum-Fotwe, F.T., (2007). Training levy to support construction
craft skills training in Zambia. West Indian Journal of Engineering, 30(1), 37–44.
Muya, M., Kaliba, C., Sichombo, B. & Shakantu, W., (2013). Cost escalation, schedule
overruns and quality shortfalls on construction projects: The case of Zambia. International Journal of Construction Management, 13(1), pp.53-68.
Mwanaumo, E. M., Thwala, W. D. & Mambwe, M., 2018. Multi Stakeholder Consultative
Framework for Construction Health and Safety: Role of Client and Project Manager. Livingstone, Zambia, DII Conference Series, pp. 235-246.
Nasir, H., Haas, C.T., Rankin, J.H., Fayek, A.R., Forgues, D. & Ruwanpura, J., (2012).
Development and implementation of a benchmarking and metrics program for construction performance and productivity improvement. Canadian Journal of Civil Engineering, 39(9), 957–967.
National Council for Construction, (2004). Development of contractor registration scheme with
a focus on small-scale civil works contractors: final report.
National Council for Construction, (2021). Annual Report. Lusaka.
Neely, A., (1998). Three modes of measurement: theory and practice. International journal of
business performance management, 1(1), 47–64.
Neuman, W. L. (2003). Social Research Methods: Qualitative and Quantitative Approaches,
Relevance of social research, Vol. 8, available at: http://books.google.fr/books?id=nObtAAAAMAAJ.
Ngoma, S., Muya M., and Kaliba, C., 2014. Benefits, Constraints and Risks in Infrastructure
Development via Public-Private Partnerships in Zambia. Journal of Construction in Developing Countries, 19(1), pp 15-33.
Ngoma, S., Mwanaumo, E. M., & Kaliba, C., (2024). Measuring Productivity in Labour-
Intensive Construction Projects in Zambia. Journal-Innovation, 76 (2), pp 476-485.
Ngomi, A., (2017). Factors affecting project performance among local contractors. The
International Journal of Multi-Disciplinary Research ISSN, 3471–7102.
Nguyen, Q. T., Van Tam, N., Dinh, T. H. & Quy, N. L. D., (2020). Critical factors affecting
labour productivity within construction project implementation: a project manager's perspective. Entrepreneurship and Sustainability Issues, 8(2), 751.
Nyoni, T. & Bonga, W.G., 2016. An empirical investigation of factors affecting construction
sector labour productivity in Zimbabwe. International Journal of Business and Management Invention (IJBMI), 5(8), 68-79.
Ofori G., (2000). The knowledge-based economy and construction industries in developing
countries. Proceedings: CIB W107 1st International conference: Creating a sustainable construction industry in developing countries, 11 to 13 November 2000, Stellenbosch, South Africa.
Ohueri, C.C., Enegbuma, W.I., Wong, N.H., Kuok, K.K. & Kenley, R., (2018). Labour
productivity motivation framework for Iskandar Malaysia. Built Environment Project and Asset Management, 8(3), pp.293-304.
O’Grady, J. & McCabe, B., (2014). Productivity in the construction industry: concepts, trends,
and measurement issues. University of Toronto.
Olomolaiye, P., Kaming, P., Holt, G., & Harris, F. (1996). "Factors influencing craftsmen’s
productivity in Indonesia", Int. J. Proj. Manag., 15, (1), 21-30.
Oo, B. L. & Lim, B.T.H. (2023). Women Workforces’ Satisfaction with Personal Protective
Equipment: A Case of the Australian Construction Industry. Buildings, 13(4), 959.
Palikhe, S., Kim, S. & Kim, J. J., (2019). Critical success factors and dynamic modeling of
construction labour productivity. International Journal of Civil Engineering, 17(3), 427-442.
Polta, G., & Arditi, P. (2005). The JIT Management System in developing countries”
Construction Management and Economics, 23(7), 697-712.
Poole, M. A., & O'Farrell, P. N., (1971). The assumptions of the linear regression
model. Transactions of the Institute of British Geographers, 145–158.
Porter, M., (1990). The Competitive Advantage of Nations. New York: The Free Press.
Rose, N., (1996). The death of the social? Re-figuring the territory of government. International
Journal of Human Resource Management, 25(3), 327–356.
Sampa, C., (2016). An evaluation of Worker's welfare facilities and its effects on productivity
in the Zambian Construction Industry (Masters dissertation, University of Zambia).
Sylvia, C., (2017). An Investigation into the factors affecting project performance among
contractors in Lusaka District of Zambia.
Thwala, W. D., (2007). Challenges facing labour-intensive public works programmes and
projects in South Africa. International Journal of Construction Management, 7(2), 1-9.
Van Thanh, L., (2016). Relationship at work as a cause of occupational stress: the case of
academic women in Vietnam. International journal of mental health systems, 10, pp.1-15.
Vogl, B., & Abdel-Wahab, M., (2015). Measuring the construction industry’s productivity
performance: Critique of international productivity comparisons at industry level. Journal of construction engineering and management, 141(4), 04014085.
Wu, J., Du, H., Li, X. &Li, P., (2010). Creating and Delivering a Successful Knowledge
Management Strategy, in Russ, M. (Ed.), Knowledge Management Strategies for Business Development, Business Science Reference, Hershey, pp. 261–272.
Yi, W. & Chan, A.P., (2014). A critical review of labour productivity research in construction
journals. Journal of Management in Engineering, 30(2), 214–225.
Zhao, T. & Dungan, J. M., (2014). Improved baseline method to calculate lost construction
productivity. Journal of Construction Engineering and Management, 140(2), p.06013006.
Zhou, W. & He, J.M., (2013). Generalized GM (1, 1) model and its application in forecasting
of fuel production. Applied Mathematical Modelling, 37(9), pp.6234-6243.
Downloads
Published
Issue
Section
Categories
License
Copyright (c) 2025 AFRICAN JOURNAL OF APPLIED RESEARCH

This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.
By submitting and publishing your articles in the African Journal of Applied Research, you agree to transfer the copyright of the Article from the authors to the Journal ( African Journal of Applied Research).